BTMC Issues - From RCA Perspective-2

 This is in continuation of my last post.  This time I thought to take delayed disturbed scheduling. As you all aware, RCA is simple technique to find out root causes and thus first step to eliminate bad causes. Some of the caused may be repetitive from last post. But if repeated it should be considered as a major cause and should be given priority.

 

Effect  -

Buses not operating in time thus causing inconvinience to public and to BMTC scheduling system itself

Causes  due to - 

1. Traffic Jam at Signal due to

         -> Long Signals

         -> Heavy Vehicle Rush

         -> No traffic Management in junctions

         -> No signal

2. Traffic Jam at Roads due to

Commissioning of Doubling Track between Dharwad Mugad

SWR has given press notice that on 18.03.2010 will conduct the speed trial on Dharwad to Mugad ( 14 Kms ) on newly laid double line.

Now We have double line laid recently between Hubli to Hebsur 19 Kms towards Gadag & Arsikere and Devanur (14 km). With this Dharwad to Kambargavi ( 20 Kms ) Yesvanthpur to Londa has got further boost on double track slowly. We have double track from Hubli junction upto Hubli South Station ( 6 Kms ) towards Kundagol

http://lite.epaper.timesofindia.com/getpage.aspx?pageid=22&pagesize=&edid=&edlabel=TOIBG&mydateHid=18-03-2010&pubname=&edname=&publabel=TOI

Now Hubli-Dharwad twin city can have local trains with DEMU trains running on the double track. Train can run between Dharwad ( from Karnataka University ) upto Gadag or Kundagol with so many station on the way, many educational colleges & major Hospitals.  SWR should  start working on starting local train.

BMLTA sub committee 6th meeting on 14th Dec'2009

BMLTA Sub Committtee minited of meeting held on 14th Dec'2009,  Principal Secretary, Infrastructure Development Department.
Here things are clear on starting of services between Yesvanthpur to Anekal and DRM of SWR has agreed finally to start the services between Yesvanthpur to Anekal once they get the Amount for two Rakes.

Effect of Metro stations on adjacent roads

The metro work is underway on main roads in most part of Bangalore. The metro stations that are to be constructed are significantly wider than the main track. Will this not create bottlenecks on adjacent roads? For example, there is a metro station being constructed on Old Madras Road near the 80ft road junction. The Old Madras road which is wider on either side of the station suddenly becomes very narrow leading to frequent traffic jams here. Even after the construction of the station, the road width isn't going to change and this can be a serious problem later on. 

Consider the Vijaynagar main road. If the Metro station is constructed near the Bunts Sangha, it will almost be as wide as the road today. How can  the width of the roads be made uniform throughout?

Is this something that BMRCL is thinking of? In addition, the presence of a station will require rickshaw stands and bus stops nearby which means the roads have to be wider in these places. On the contrary, the station makes the road narrower. This is definitely a double whammy. 

Mysore road expansion - how can you remove the bottleneck?

Do planners in Bangalore realize that bottlenecks are the main source of traffic problems? It doesn't matter if you have a 5km long 8 lane road at the end of which has a bottleneck which reduces to 2 lanes. 

It looks like that the Mysore road is going to be widened. The govt will end up spending crores of money and cause inconvenience to lot of riders during this widening spree. We'll also lose all the trees which so far have kept the Mysore road a complete canopy. But the Bapujinagar bridge is a huge bottleneck. If nothing is done to widen at this point, the whole effort is meaningless. Given that we have the Masjid and the GhaaLi Anjaneya temple on either side, we can imagine that this part of the road can never be widened. 

Do the officials even think about this before going about doing their job of road widening? 

Transport Hub at Mangalore

The plan to build a large, formal bus stand for Mangalore had been conceived some years ago. Mangalore's original bus stand at Hampankatta had been too small with no scope for any expansion as it had been sandwiched right in the heart of town (CBD). Hence, KSRTC had shifted out to a newer facility of it's own long ago, however private buses continued to use the same bus-stand. With efflux of time, increased number of buses & severe congestion, the inter-city bus stand was moved to Statebank, close to the fishing harbour, which had long been the terminus for intra-city buses (The Hampankatta bus stand is now a convenient parking facility). Within a few years, due to increasing growth rate/s, much higher number of buses & space constraints, the need for a much larger facility was becoming more & more acute.

Chikka Circle Buses (K service)

There has been sightings of new route prefixed with "K" near Koramangla. The same has been confirmed by http://btis.in

K service or the Chikka Circle service has been started recently by BMTC. Following are the routes:

  • K1: St. Johns Hospital to Yeshvantapur via Domlur,Trinity Circle,Indian Express and Mekhri Circle
  • K2: Chikkamaranhalli to MCTC via Yeshvantapur,Isckon,Shankarmutt,Vijayanagar
  • K3: Vijayanagar to Koramangla via MCTC,Chamrajpet,Jayanagar bus stand,Carmel Convent and Dairy Circle.

 

BMRCL Ph II DPR route?

Naveen presented a good summary of his meeting with BMRCL

One thing that came of that was the DPR for the phase II was in the final stages and would be out soon..there are already questions on

Autos - help them to help ourselves

Couple of months ago I read in paper about the government subsidy for auto rickshaws to change from 2 stroke to 4 stroke engine.  I felt that it was wonderful and very pro-active approach to reducing the pollution.   2 stroke engines pollute 4 times more than cars (because of the pre-mix of oil

Pedestrian skywalk at ORR/OMR chaos, finally

I am not a fan of skywalks (prefer regular ped-signals, or underpass), but the chaos that this place is - Outer Ring Road/Old Madras Road junction near Tin Factory, K R Puram - a pedestrian skywalk to cross 8 lanes of thick traffic should help. After our last round of complaints etc, the pedestrian signals had been operating for some time, they still are - either the light turns red, or cops stop traffic to let pedestrians cross. The skywalk (such a late arrival) is perhaps part of signal-free ORR project.

 

Praja.in comment guidelines

No foul language, hate mongering or personal attacks. If criticizing third person or an authority, you must be fact based, as constructive as possible, and use gentle words. Avoid going off-topic no matter how nice your comment is. Moderators reserve the right to either edit or simply delete comments that don't meet these guidelines. If you are nice enough to realize you violated the guidelines, please save Moderators some time by editing and fixing yourself. Thanks!